Home > Business > NTPC Darlipali plant’s second unit to start commercial operation from Sept 1

NTPC Darlipali plant’s second unit to start commercial operation from Sept 1

TBB BUREAU

BHUBANESWAR, AUG 31, 2021

           State-run power giant NTPC on Tuesday said the second unit of Darlipali Super Thermal Power Station in Sundargarh district of Odisha will start commercial operation from September 1.

“The second unit of the power plant with 800MW capacity that completed its trial operation on July 21 will start commercial generation from September 1, 2021,” informed NTPC Regional Executive Director (Eastern Region) SK Satya.

The Unit-1 of Darlipali power project had started commercial operation in March 2020.

With this, the commercial capacity of NTPC and NTPC group will become 53,225 MW and 66,650 MW respectively.

Odisha will get 50 per cent of the power generated from the Darlipali Power Project of 1600 MW (2X800 MW), while the remaining 50 per cent will be sold to Bihar, Jharkhand, Sikkim, and West Bengal.

 As per the power purchase agreement with the Central Electricity Regulatory Commission (CERC), the cost of power from the Darlipali plant will be Rs 2.90 per unit. While the fixed cost of power is set at Rs. 1.90 per unit, the variable cost (ECR) has bent determined at Re 1 per unit.

NTPC has already spent over Rs. 13,500 core in the project that is estimated at Rs. 13,700 crore. Some of the works like construction of railway line for transportation of coal and construction of merry go round (MGR) linking to railway sidings at Laikera and Kechobahal stations at Jharsuguda district for coal dispatch to the plant are under progress, and are likely to be completed by June 2022, NTPC said in a statement.

The construction of the railway lines and MGR was delayed due to land acquisition problems. However, the Issues were resolved after the Cabinet Committee on Investment (CCI) took up the matter with the State Government in January 21.Installation of Flue Gas Desulphurization (FGD) system to curb SOx missions is under progress and this will be completed by next year.

The pit head-based thermal power plant is currently sourcing its requirement of fossil fuel from its Dulanga coal mines at Sundargarh. With a daily requirement of about 25,000 tonne, the Dulanga mine has the capacity to meet 20,000 tonne. The balance requirement will be met from Mahanadi Coalfields Limited through road. “Once the MGR project is over, NTPC will meet the additional coal requirement from anywhere in the country through railway.” Satya added.

 Water for the plant is sourced from the Hirakud reservoir through a pipeline covering a distance of about 45 km from the project site. The first unit of the plant was commissioned on 1st March, 2020.

About admin

Leave a Reply

Your email address will not be published. Required fields are marked *

*