All affected 33 kV feeders, 33/11 kV substations and power transformers fully restored; over 6,500 personnel mobilised across eight districts

 

THEBUSINESSBYTES BUREAU

BERHAMPUR, NOVEMBER 20, 2026

Demonstrating its operational preparedness and rapid disaster-response capabilities, TP Southern Odisha Distribution Limited (TPSODL) has restored electricity supply to 10,69,026 consumers, achieving an impressive 98.68 per cent restoration across its eight-district operational area within just seven hours of Cyclone Akvan's impact. Marking a significant milestone in the large-scale restoration operation, the company successfully restored all affected 33 kV feeders, 33/11 kV substations and power transformers, reflecting the coordinated efforts of its frontline teams, extensive manpower mobilisation and robust emergency response mechanism.

Cyclone Akvan crossed the North Andhra Pradesh–South Odisha coast near Gopalpur, bringing strong winds and heavy rainfall that disrupted electricity distribution infrastructure across several parts of Southern Odisha. Responding swiftly to the situation, TPSODL mobilised more than 6,500 personnel across Ganjam, Gajapati, Rayagada, Koraput, Malkangiri, Nabarangpur, Kandhamal and Boudh districts. Dedicated teams were deployed on the ground to assess infrastructure damage, undertake repairs and progressively restore electricity supply to affected consumers, prioritising the restoration of critical network infrastructure and connectivity to communities.

The restoration drive recorded significant progress across all levels of the distribution network. TPSODL successfully restored all six affected 33 kV feeders, all 19 affected 33/11 kV Power Substations (PSS) and all 42 affected Power Transformers (PTRs). Furthermore, out of 365 affected 11 kV feeders, 364 had been restored, while 35,749 affected Distribution Transformers (DTRs) had also been brought back into service. These achievements highlight the scale of the restoration exercise and the systematic approach adopted by the company to bring the electricity distribution network back to normalcy in the aftermath of the cyclone.

The district-wise restoration progress further reflected the extensive efforts undertaken by TPSODL's field teams. Ganjam recorded 99.76 per cent restoration, followed by Koraput at 99.53 per cent, Gajapati at 98.90 per cent, Rayagada at 98.06 per cent, Nabarangpur at 98.01 per cent, Boudh at 97.55 per cent and Kandhamal at 94.23 per cent. Malkangiri achieved 100 per cent restoration. The remarkable progress across all eight districts was made possible through extensive field-level coordination, prompt deployment of technical personnel and sustained repair operations to reconnect affected consumers and restore essential electricity services.

The large-scale restoration operation was backed by TPSODL's comprehensive cyclone preparedness and emergency response arrangements, put in place well ahead of the weather event. The company had prepared a deployment plan covering 6,474 personnel, supported by around 800 skilled and unskilled project personnel, additional standby manpower and specialised restoration resources. The preparedness measures included mobile distribution substations, dedicated vehicles, emergency repair equipment, lighting arrangements, diesel generator (DG) sets, tree-pruning units and strategically positioned transit stores to ensure the timely availability of essential materials at critical locations. Control centres remained actively engaged with field-level teams to monitor network conditions, coordinate restoration activities and facilitate swift responses to emerging challenges across the operational area.

Commenting on the restoration efforts, Amit Kumar Garg, CEO, TPSODL, said, “Restoring electricity supply swiftly following a cyclone of this magnitude requires meticulous advance preparedness, seamless coordination and the collective commitment of teams working tirelessly on the ground. Our teams were mobilised across Southern Odisha to ensure that electricity supply was restored safely and at the earliest to affected consumers. Achieving nearly 99 per cent restoration within seven hours, including the restoration of all affected 33 kV feeders, substations and power transformers, reflects the dedication of our frontline personnel and the strength of our emergency response mechanism. I sincerely appreciate our employees, contractors and field teams for their tireless efforts, determination and commitment during this challenging period. We remain focused on ensuring reliable power supply to our consumers while continuously strengthening the resilience and preparedness of our distribution network to respond effectively to future challenges.”

The swift restoration of electricity supply following Cyclone Akvan underscores the critical importance of advance planning, resilient distribution infrastructure, effective emergency response mechanisms and coordinated field operations in maintaining the continuity of essential services during extreme weather events. The achievement also highlights the contribution of dedicated frontline personnel, whose timely intervention and sustained efforts play a vital role in restoring normalcy in cyclone-affected communities.

TPSODL continues to strengthen its operational capabilities, emergency preparedness systems and distribution network resilience through focused investments, technological interventions and enhanced response mechanisms, reaffirming its commitment to delivering safe, reliable and uninterrupted electricity services to consumers across Southern Odisha.