All affected 33 kV feeders, 33/11 kV
substations and power transformers fully restored; over 6,500 personnel
mobilised across eight districts
THEBUSINESSBYTES BUREAU
BERHAMPUR, NOVEMBER 20, 2026
Demonstrating its operational preparedness and rapid disaster-response
capabilities, TP Southern Odisha Distribution Limited (TPSODL) has restored
electricity supply to 10,69,026 consumers, achieving an impressive 98.68 per
cent restoration across its eight-district operational area within just seven
hours of Cyclone Akvan's impact. Marking a significant milestone in the
large-scale restoration operation, the company successfully restored all
affected 33 kV feeders, 33/11 kV substations and power transformers, reflecting
the coordinated efforts of its frontline teams, extensive manpower mobilisation
and robust emergency response mechanism.
Cyclone Akvan crossed the North Andhra Pradesh–South Odisha coast near
Gopalpur, bringing strong winds and heavy rainfall that disrupted electricity
distribution infrastructure across several parts of Southern Odisha. Responding
swiftly to the situation, TPSODL mobilised more than 6,500 personnel across
Ganjam, Gajapati, Rayagada, Koraput, Malkangiri, Nabarangpur, Kandhamal and
Boudh districts. Dedicated teams were deployed on the ground to assess
infrastructure damage, undertake repairs and progressively restore electricity
supply to affected consumers, prioritising the restoration of critical network
infrastructure and connectivity to communities.
The restoration drive recorded significant progress across all levels of
the distribution network. TPSODL successfully restored all six affected 33 kV
feeders, all 19 affected 33/11 kV Power Substations (PSS) and all 42 affected
Power Transformers (PTRs). Furthermore, out of 365 affected 11 kV feeders, 364
had been restored, while 35,749 affected Distribution Transformers (DTRs) had
also been brought back into service. These achievements highlight the scale of
the restoration exercise and the systematic approach adopted by the company to
bring the electricity distribution network back to normalcy in the aftermath of
the cyclone.
The district-wise restoration progress further reflected the extensive
efforts undertaken by TPSODL's field teams. Ganjam recorded 99.76 per cent
restoration, followed by Koraput at 99.53 per cent, Gajapati at 98.90 per cent,
Rayagada at 98.06 per cent, Nabarangpur at 98.01 per cent, Boudh at 97.55 per
cent and Kandhamal at 94.23 per cent. Malkangiri achieved 100 per cent
restoration. The remarkable progress across all eight districts was made
possible through extensive field-level coordination, prompt deployment of
technical personnel and sustained repair operations to reconnect affected
consumers and restore essential electricity services.
The large-scale restoration operation was backed by TPSODL's
comprehensive cyclone preparedness and emergency response arrangements, put in
place well ahead of the weather event. The company had prepared a deployment
plan covering 6,474 personnel, supported by around 800 skilled and unskilled
project personnel, additional standby manpower and specialised restoration
resources. The preparedness measures included mobile distribution substations,
dedicated vehicles, emergency repair equipment, lighting arrangements, diesel
generator (DG) sets, tree-pruning units and strategically positioned transit
stores to ensure the timely availability of essential materials at critical
locations. Control centres remained actively engaged with field-level teams to
monitor network conditions, coordinate restoration activities and facilitate
swift responses to emerging challenges across the operational area.
Commenting on the restoration efforts, Amit Kumar Garg, CEO, TPSODL,
said, “Restoring electricity supply swiftly following a cyclone of this
magnitude requires meticulous advance preparedness, seamless coordination and
the collective commitment of teams working tirelessly on the ground. Our teams
were mobilised across Southern Odisha to ensure that electricity supply was
restored safely and at the earliest to affected consumers. Achieving nearly 99
per cent restoration within seven hours, including the restoration of all
affected 33 kV feeders, substations and power transformers, reflects the
dedication of our frontline personnel and the strength of our emergency
response mechanism. I sincerely appreciate our employees, contractors and field
teams for their tireless efforts, determination and commitment during this
challenging period. We remain focused on ensuring reliable power supply to our
consumers while continuously strengthening the resilience and preparedness of
our distribution network to respond effectively to future challenges.”
The swift restoration of electricity supply following Cyclone Akvan underscores the critical importance of advance planning, resilient distribution infrastructure, effective emergency response mechanisms and coordinated field operations in maintaining the continuity of essential services during extreme weather events. The achievement also highlights the contribution of dedicated frontline personnel, whose timely intervention and sustained efforts play a vital role in restoring normalcy in cyclone-affected communities.
TPSODL continues to strengthen its operational capabilities, emergency preparedness systems and distribution network resilience through focused investments, technological interventions and enhanced response mechanisms, reaffirming its commitment to delivering safe, reliable and uninterrupted electricity services to consumers across Southern Odisha.