The state has converted applications into installations at a
rate above the national average, but the size of its rooftop solar systems
remains significantly lower, says PRIYABRAT BISWAL
India's rooftop solar
programme, PM Surya Ghar: Muft Bijli Yojana, is entering a phase in which
the quality and scale of implementation matter as much as the number of
households showing interest. The programme, launched by the Union government in
February 2024, seeks to accelerate residential rooftop solar adoption across
the country and ultimately cover one crore households. With substantial central
financial assistance available to eligible consumers, the scheme has created an
unprecedented opportunity to take solar generation from large power plants to
millions of individual homes.
The performance
figures for India and Odisha offer an intriguing picture of how that transition
is progressing. Odisha has generated
3,46,304 applications under the scheme and has converted 2,11,221 of them into
installations, adding 486.25 MW of rooftop solar capacity. At the national
level, 82,87,664 applications have resulted in 48,05,658 installations with a
cumulative capacity of 16,902.92 MW. On the surface, Odisha's contribution
represents a relatively modest share of the national programme. But a closer
examination reveals that the state's performance cannot be judged simply by
comparing the absolute number of applications or installations with India's
much larger figures.
The most revealing
measure is the rate at which applications have translated into completed installations. Nationally,
the conversion works out to approximately 58 per cent. Odisha's corresponding
figure is nearly 61 per cent. In practical terms, this means that Odisha has
converted a slightly larger proportion of its applicant base into actual
rooftop solar installations than the country as a whole. The state therefore
does not appear to be facing a fundamental problem of converting consumer
interest into completed systems. Indeed, on this particular parameter, Odisha
is marginally ahead of the national average.
The picture changes
when installed capacity is brought
into the equation. India's 48.06 lakh installations have produced 16,902.92 MW,
which translates into an average installed capacity of roughly 3.52 kW per
installation. Odisha, despite having more than 2.11 lakh installations, has
added 486.25 MW, giving an average of only around 2.30 kW per installation. The
difference is substantial. The average rooftop system installed in Odisha is
about one-third smaller than the national average.
This capacity differential is the central
issue emerging from the figures. Odisha accounts for around 4.2 per cent of the
country's applications and about 4.4 per cent of its installations, but its
share of installed capacity is only about 2.9 per cent. In other words, the
state is producing installations broadly in line with its share of
applications, yet those installations are generating considerably less capacity
than the national pattern would suggest.
The same conclusion
emerges when capacity is considered against the application base. India's 82.88
lakh applications correspond to approximately 2.04 kW of installed capacity for
every application. Odisha's 3.46 lakh applications correspond to only about
1.40 kW per application. That places Odisha roughly 31 per cent below the
national level on this measure. The gap becomes even more pronounced when
completed installations are considered, with Odisha's average of about 2.30 kW
compared with India's 3.52 kW.
This does not
necessarily mean that Odisha's rooftop solar programme is administratively
weaker than the national programme. The size of an individual rooftop system
depends on several factors, including household electricity consumption, roof
area, sanctioned load, consumer investment decisions and the technical
suitability of individual properties. A larger number of small systems can
therefore produce fewer megawatts than a smaller number of larger
installations. Nevertheless, the figures establish a clear capacity gap, and
that gap is important because the ultimate energy impact of rooftop solar
depends on generation capacity rather than merely the number of installations.
The experience of
Odisha's four distribution companies adds another layer to the analysis. Their
individual performance shows that the state's overall position conceals
considerable variation in the pace and character of implementation.
TP
Central Odisha Distribution Ltd has the largest
application base among the four, with 1,14,413 applications, of which 68,252
have resulted in installations. Its installed capacity stands at 169.64 MW. The
conversion rate is therefore close to 60 per cent, broadly comparable with the
national figure and slightly below Odisha's overall rate. What distinguishes
the Central DISCOM is the size of the systems being installed. Its average
capacity per completed installation works out to around 2.49 kW, the highest
among Odisha's four distribution companies. Even so, this remains substantially
below the national average of about 3.52 kW.
TP
Western Odisha Distribution Ltd presents a different
picture. It has received 86,593 applications and completed 57,892
installations, resulting in a conversion rate of almost 67 per cent. This is
the highest among the four Odisha DISCOMs and is also clearly above the national
average. Its installed capacity of 139.65 MW gives an average system size of
roughly 2.41 kW. Western Odisha thus demonstrates that a comparatively high
rate of application-to-installation conversion can be achieved, although the
capacity associated with each installation remains below the national
benchmark.
TP
Northern Odisha Distribution Ltd has received 84,947
applications and completed 54,435 installations, giving it a conversion rate of
approximately 64 per cent. Its performance on this measure is also comfortably
above the national average. However, its 115.87 MW of installed capacity
translates into an average system size of about 2.13 kW. The Northern DISCOM
therefore has a relatively strong conversion record but a more modest capacity
outcome.
The most pronounced
gap appears in TP Southern Odisha
Distribution Ltd. Against 60,496 applications, the DISCOM has completed
30,784 installations, producing a conversion rate of approximately 51 per cent.
That is below both the national average and Odisha's overall conversion rate.
Its installed capacity of 61.24 MW is also the lowest among the four DISCOMs,
while its average system size is approximately 1.99 kW, again the lowest in the
state.
The DISCOM-wise figures consequently point
towards different implementation challenges rather than one uniform statewide
problem. Central Odisha has the largest scale and the highest average
installation capacity. Western Odisha has the strongest conversion of
applications into installations. Northern Odisha combines a high conversion
rate with a moderate system size. Southern Odisha, by contrast, has room for
improvement in both the conversion of applications and the capacity realised
from completed installations.
This distinction is
important for assessing the next phase of PM Surya Ghar in Odisha. If
performance is judged only by the number of applications received, the emphasis
remains on generating consumer demand. If installations are the principal
measure, the focus shifts towards processing applications, completing technical
formalities and connecting systems to the grid. But once a state reaches a
reasonably high installation conversion rate, the next question has to be how
much generating capacity those installations are creating.
Odisha's figures
suggest that this is now the more significant question. The state has already
demonstrated that applications can be converted into installations at a rate
slightly better than the national average. The
challenge is to raise the capacity intensity of those installations. At the
present average of around 2.30 kW per installation, Odisha would need either more installations of larger capacity or a
greater proportion of households opting for systems capable of meeting a larger
share of their electricity requirements.
The scale of the
potential gap becomes apparent through a simple comparison. If Odisha's
existing installations had the same average capacity as installations
nationally, the state's installed capacity would be considerably higher than
the reported 486.25 MW. Similarly, if the state's applications were producing
capacity at the national average rate, the resulting capacity would also be
substantially greater. These comparisons should not be interpreted as targets
or forecasts, since household characteristics differ across regions, but they
demonstrate the magnitude of the capacity-intensity difference.
The issue also has
implications for the role of DISCOMs. Under a rooftop-solar programme, the
distribution company becomes a crucial part of the implementation chain.
Consumer awareness may generate an application, but the journey from
application to a functioning rooftop system involves technical assessment,
approvals, installation, inspection, metering and grid connectivity. The
differences between the four Odisha DISCOMs indicate that the pace of this
chain is not uniform across the state.
The relatively high conversion rates in Western
and Northern Odisha suggest that significant portions of the application
pipeline can be taken through to installation efficiently. Southern Odisha's
lower conversion rate indicates that the application pipeline there requires
closer examination. The reasons could range from consumer-side decisions and
financing constraints to technical, procedural or connectivity-related issues,
and the available figures alone cannot establish which factors are responsible.
What the numbers do show is where the implementation gap is most visible.
At the same time, the
capacity figures suggest that improving conversion alone will not close
Odisha's national gap. Even the DISCOM with the highest conversion rate has an
average system size well below the national level. This makes system capacity
an important second-generation performance indicator for the programme.
The broader
significance of PM Surya Ghar lies in its potential to transform ordinary
electricity consumers into distributed generators. Instead of rooftop solar
being limited to a relatively small group of households with the financial
means and technical inclination to install systems independently, the scheme
seeks to make residential solar adoption a mass phenomenon. The scale of
India's numbers — more than 82 lakh applications and over 48 lakh installations
in the figures under consideration — illustrates the enormous demand that has
emerged around the programme.
Odisha has
established a substantial presence within that national effort. More than three
lakh applications and over two lakh installations represent a sizeable
rooftop-solar base for the state. The state's installation conversion rate also
indicates that consumer interest is not merely remaining on paper. The concern is that the capacity being
added per installation is significantly lower than the national level.
That makes Odisha's
next challenge more qualitative than quantitative. Increasing the number of
installations remains important, particularly in areas where application
conversion is relatively weak, but equal attention needs to be given to the
capacity of the systems being installed. A programme that succeeds in placing solar
panels on a very large number of rooftops but predominantly through smaller
systems will have a different energy impact from one that achieves a comparable
installation count with substantially higher average capacity.
The figures therefore
suggest that Odisha should assess PM
Surya Ghar through two complementary lenses. The first is implementation efficiency — how
successfully applications are being converted into operational rooftop systems.
The second is capacity efficiency — how
much solar generating capacity is being created through those installations. On
the first measure, Odisha compares favourably with the national average. On the
second, a significant gap remains.
For the four DISCOMs,
the lesson is equally differentiated. The stronger conversion performance
visible in Western and Northern Odisha offers evidence of a relatively
efficient application-to-installation pipeline, while Central Odisha's higher
average system capacity shows the potential for increasing the capacity
contribution of individual installations. Southern Odisha's comparatively low
conversion and smaller average system size make it the clearest area for
further investigation and improvement.
Ultimately, the
success of PM Surya Ghar in Odisha will not be captured adequately by a
single number. Applications show the level of public participation;
installations demonstrate the programme's ability to turn interest into
physical assets; and megawatts reveal the actual scale of renewable-energy
capacity being created. Odisha has made meaningful progress from the first
stage to the second. The data now indicate that the next test is the distance
it can travel from installations to higher-capacity rooftop generation.
The state's
rooftop-solar story, therefore, is neither one of broad underperformance nor
one of complete convergence with the national picture. It is a story of
stronger-than-national-average conversion accompanied by a substantial capacity
gap. Closing that gap — while improving
conversion in weaker-performing areas — will determine how effectively Odisha can translate the momentum
generated by PM Surya Ghar into a deeper and more productive residential
solar revolution.
(The views expressed in this article are
those of the author and do not necessarily reflect the views of this website or
its management. The author may be reached at: [email protected])